Time & Work Questions for SSC CGL Quantitative Aptitude

Time & Work questions test work rates — how long individuals or groups take to finish a job together, wages split by work done, and pipes filling or emptying tanks. Parikshala's question bank has 22 exam-pattern Time & Work questions for SSC CGL, each with a step-by-step solution (5 easy, 14 medium, 3 hard). Quantitative Aptitude carries 50 of 200 marks in SSC CGL Tier-I (Prelims).

What Time & Work Questions Test

  • Individual and combined work rates
  • Work with people joining or leaving midway
  • Wages divided in ratio of work done
  • Pipes and cisterns (filling vs emptying rates)
  • Efficiency comparisons (A is twice as fast as B)

Question bank coverage by sub-pattern

· 10Basic Time and Work · 9Pipes and Cisterns · 3

How Time & Work Appears in SSC CGL

25
Quantitative Aptitude questions in Tier-I (Prelims)
50
marks for the section (of 200 total)
60 min
Tier-I (Prelims) duration
0.50
negative marks per wrong answer

Time & Work is part of the Quantitative Aptitude section (25% of the SSC CGL syllabus). See the full SSC CGL Tier-I breakdown.

Time & Work Solved Examples for SSC CGL

Exam-pattern questions from the practice bank, with full solutions.

1Hard

If 6 men and 8 women can complete a work in 10 days, and 26 men and 48 women can complete it in 2 days, find the time taken by 15 men and 20 women to complete the work.

  1. A.4 daysCorrect
  2. B.5 days
  3. C.3 days
  4. D.6 days

Solution

Let 1 man's 1 day work = m and 1 woman's 1 day work = w. (6m + 8w) x 10 = 1 => 60m + 80w = 1 ...(1) (26m + 48w) x 2 = 1 => 52m + 96w = 1 ...(2) From (1) and (2): 60m + 80w = 52m + 96w => 8m = 16w => m = 2w. Substitute in (1): 60(2w) + 80w = 1 => 200w = 1 => w = 1/200, m = 1/100. 15 men + 20 women = 15/100 + 20/200 = 15/100 + 10/100 = 25/100 = 1/4 per day. Days = 4.

2Medium

Ram and Ramesh can do a work in 12 days, Ramesh and Somesh in 15 days and Somesh and Ram in 10 days. If Ram, Ramesh and Somesh work together, in how many days will they complete the work?

  1. A.10
  2. B.8Correct
  3. C.12
  4. D.6

Solution

Let R, Ra, and S be the work done by Ram, Ramesh and Somesh in 1 day. R + Ra = 1/12, Ra + S = 1/15, S + R = 1/10. Adding all, 2(R + Ra + S) = 1/12 + 1/15 + 1/10 = (5+4+6)/60 = 15/60 = 1/4. R + Ra + S = 1/8. So, they will complete the work in 8 days.

3Hard

A, B and C can do a work in 10, 12 and 15 days respectively. They all start together. After 2 days, A leaves. After 2 more days, B also leaves. How many more days will C take to finish the remaining work?

  1. A.3 daysCorrect
  2. B.5 days
  3. C.4 days
  4. D.6 days

Solution

LCM(10, 12, 15) = 60 units (total work). A = 6 units/day, B = 5 units/day, C = 4 units/day. First 2 days (all three): 2 x (6+5+4) = 30 units. Next 2 days (B and C): 2 x (5+4) = 18 units. Remaining = 60 - 30 - 18 = 12 units. C alone: 12/4 = 3 days.

Time & Work — Frequently Asked Questions

What is the LCM method in time & work?

Assume the total work equals the LCM of the given days, so each person's one-day work becomes a whole number. It replaces fraction arithmetic and is the standard approach for exam-pattern questions.

How are pipes-and-cisterns questions different?

They are time & work with a negative worker: an emptying pipe subtracts its rate. Everything else — LCM totals, combined rates — works identically.

How many Time & Work practice questions does Parikshala have for SSC CGL?

22 exam-pattern Time & Work questions for SSC CGL Quantitative Aptitude, each with a step-by-step solution. Practice is free — no sign-up needed to start.

More SSC CGL Quantitative Aptitude Topics

Every topic links to its own practice set with solutions.

Join Our Telegram Community

Daily GK questions, exam notifications, free mock test links, and peer discussion

Join Channel

Practice Time & Work for SSC CGL

22 exam-pattern questions with step-by-step solutions. Start free — no sign-up needed.