What Time & Work Questions Test
- Individual and combined work rates
- Work with people joining or leaving midway
- Wages divided in ratio of work done
- Pipes and cisterns (filling vs emptying rates)
- Efficiency comparisons (A is twice as fast as B)
How Time & Work Appears in SSC CHSL
Time & Work is part of the Quantitative Aptitude section (25% of the SSC CHSL syllabus). See the full SSC CHSL Tier-I breakdown.
Time & Work Solved Examples for SSC CHSL
12 exam-pattern time & work questions from the practice bank, each with a full solution. Tap an option to check your answer.
A and B together can do a work in 10 days. A alone can do it in 15 days. In how many days can B alone do the work?
Tap an option to answer, or show the solution
Answer: C. 30 days
B's 1-day work = 1/10 - 1/15 = (3 - 2)/30 = 1/30. B alone takes 30 days.
A tap fills a bath in 12 minutes and another empties it in 18 minutes. When both are opened, how long will it take to fill the bath?
Tap an option to answer, or show the solution
Answer: C. 36 minutes
Net rate per minute = 1/12 - 1/18 = (3 - 2)/36 = 1/36. Time = 36 minutes.
Two pipes A and B can fill a tank in 15 hours and 20 hours respectively, while a third pipe C can empty the full tank in 25 hours. All three pipes are opened in the beginning. After 10 hours, C is closed. In how much total time will the tank be full?
Tap an option to answer, or show the solution
Answer: A. 12 hours
Capacity = LCM(15, 20, 25) = 300 units. A = 20, B = 15, C = -12 units/hour. In first 10 hours: 10 × (20 + 15 - 12) = 10 × 23 = 230 units. Remaining = 300 - 230 = 70 units. With C closed, (A + B) fill at 35 units/hour: 70 / 35 = 2 hours. Total time = 10 + 2 = 12 hours.
Vikram can complete a piece of work in 20 days, and Sunil can complete the same work in 30 days. If they work together, in how many days will the work be completed?
Tap an option to answer, or show the solution
Answer: C. 12 days
Vikram's 1-day work = 1/20. Sunil's 1-day work = 1/30. Combined 1-day work = 1/20 + 1/30 = (3 + 2)/60 = 5/60. Total days required = 60/5 = 12 days.
Aman can complete a piece of work in 30 days, and Rohan can complete the same work in 15 days. If they work together, in how many days will the work be completed?
Tap an option to answer, or show the solution
Answer: B. 10 days
Aman's 1-day work = 1/30. Rohan's 1-day work = 1/15. Combined 1-day work = 1/30 + 1/15 = (1 + 2)/30 = 3/30. Total days required = 30/3 = 10 days.
A water tank is generally filled in 10 hours, but it takes 2 hours longer now due to a leak in its bottom. If the tank is completely full, in how many hours will the leak empty it?
Tap an option to answer, or show the solution
Answer: B. 60 hours
Filling rate with leak = 1/12. Filling rate without leak = 1/10. Leak emptying rate = 1/10 - 1/12 = (6 - 5)/60 = 1/60. Leak takes 60 hours to empty the full tank.
Vikram can complete a piece of work in 12 days, and Suresh can complete the same work in 60 days. If they work together, in how many days will the work be completed?
Tap an option to answer, or show the solution
Answer: D. 10 days
Vikram's 1-day work = 1/12. Suresh's 1-day work = 1/60. Combined 1-day work = 1/12 + 1/60 = (5 + 1)/60 = 6/60. Total days required = 60/6 = 10 days.
Rajesh can complete a piece of work in 30 days, and Rohan can complete the same work in 15 days. If they work together, in how many days will the work be completed?
Tap an option to answer, or show the solution
Answer: C. 10 days
Rajesh's 1-day work = 1/30. Rohan's 1-day work = 1/15. Combined 1-day work = 1/30 + 1/15 = (1 + 2)/30 = 3/30. Total days required = 30/3 = 10 days.
Vikas can complete a piece of work in 12 days, and Meena can complete the same work in 30 days. If they work together, in how many days will the work be completed?
Tap an option to answer, or show the solution
Answer: D. 8.57 days
Vikas's 1-day work = 1/12. Meena's 1-day work = 1/30. Combined 1-day work = 1/12 + 1/30 = (5 + 2)/60 = 7/60. Total days required = 60/7 = 8.57 days.
P can finish a piece of work in 15 days and Q can do it in 20 days. If they work together on it for 4 days, what fraction of the work is left?
Tap an option to answer, or show the solution
Answer: B. 8/15
Combined 1-day work = 1/15 + 1/20 = (4 + 3)/60 = 7/60. Work done in 4 days = 4 × (7/60) = 7/15. Fraction of work left = 1 - 7/15 = 8/15.
Two pipes A and B can fill a cistern in 12 minutes and 15 minutes respectively. If both are opened together and at the end of 3 minutes A is closed, how much more time will B take to fill the cistern?
Tap an option to answer, or show the solution
Answer: B. 8.25 minutes
Total capacity = 60 units. Rate of A = 5 units/min, B = 4 units/min. In 3 minutes, (A + B) fill 3 × (5 + 4) = 27 units. Remaining = 60 - 27 = 33 units. B takes 33 / 4 = 8.25 minutes (8 minutes 15 seconds).
Deepak can complete a piece of work in 10 days, and Neeraj can complete the same work in 30 days. If they work together, in how many days will the work be completed?
Tap an option to answer, or show the solution
Answer: D. 7.5 days
Deepak's 1-day work = 1/10. Neeraj's 1-day work = 1/30. Combined 1-day work = 1/10 + 1/30 = (3 + 1)/30 = 4/30. Total days required = 30/4 = 7.5 days.
Time & Work — Frequently Asked Questions
What is the LCM method in time & work?
Assume the total work equals the LCM of the given days, so each person's one-day work becomes a whole number. It replaces fraction arithmetic and is the standard approach for exam-pattern questions.
How are pipes-and-cisterns questions different?
They are time & work with a negative worker: an emptying pipe subtracts its rate. Everything else — LCM totals, combined rates — works identically.
How many Time & Work practice questions does Parikshala have for SSC CHSL?
197 exam-pattern Time & Work questions for SSC CHSL Quantitative Aptitude, each with a step-by-step solution. Practice is free — no sign-up needed to start.