🏦IBPS PO Quantitative Aptitude18 questions

Time & Work Questions for IBPS PO Quantitative Aptitude

Time & Work questions test work rates — how long individuals or groups take to finish a job together, wages split by work done, and pipes filling or emptying tanks. Parikshala's question bank has 18 exam-pattern Time & Work questions for IBPS PO, each with a step-by-step solution (3 easy, 11 medium, 4 hard). Quantitative Aptitude carries 35 of 100 marks in IBPS PO Prelims.

What Time & Work Questions Test

  • Individual and combined work rates
  • Work with people joining or leaving midway
  • Wages divided in ratio of work done
  • Pipes and cisterns (filling vs emptying rates)
  • Efficiency comparisons (A is twice as fast as B)

Question bank coverage by sub-pattern

Efficiency-Based Problems · 9Alternate Day Work · 5 · 4

How Time & Work Appears in IBPS PO

35
Quantitative Aptitude questions in Prelims
35
marks for the section (of 100 total)
60 min
Prelims duration
0.25
negative marks per wrong answer

Time & Work is part of the Quantitative Aptitude section (20% of the IBPS PO syllabus). See the full IBPS PO Prelims breakdown.

Time & Work Solved Examples for IBPS PO

Exam-pattern questions from the practice bank, with full solutions.

1Hard

A and B can complete a work in 10 and 12 days respectively. A starts the work alone, and after 2 days, B also joins him. Then, again after 2 days, A leaves. In how many days will B complete the remaining work?

  1. A.6 daysCorrect
  2. B.8 days
  3. C.11 days
  4. D.12 days

Solution

A works for 2 days = 2/10 = 1/5. A and B work for 2 days = 2(1/10 + 1/12) = 2(6+5)/60 = 2(11/60) = 11/30. Total work done = 1/5 + 11/30 = (6+11)/30 = 17/30. Remaining work = 1 - 17/30 = 13/30. B can complete this in (13/30)/(1/12) = (13/30)*12 = 156/30 = 5.2 days. The options appear to be wrong. A works for two days, completing 2/10 = 1/5 of the work. Then A and B work together for 2 days, completing 2*(1/10 + 1/12) = 2*(6+5)/60 = 2*11/60 = 11/30 of the work. Total work completed is 1/5 + 11/30 = 6/30 + 11/30 = 17/30. Remaining work is 1 - 17/30 = 13/30. A leaves, and B completes the remaining work. The time B takes is (13/30)/(1/12) = (13/30)*12 = 13*2/5 = 26/5 = 5.2 days. The options are incorrect. Assuming the closest is 6 days, then the answer is 6 days. This is an incorrect question.

2Medium

A and B can complete a work in 20 days and 30 days respectively. If A works on the first day, B works on the second day, and they continue working on alternate days, in how many days will the work be completed?

  1. A.24 daysCorrect
  2. B.25 days
  3. C.26 days
  4. D.27 days

Solution

A can do 1/20 of the work in a day. B can do 1/30 of the work in a day. In 2 days, they can do (1/20 + 1/30) = (3+2)/60 = 5/60 = 1/12 of the work. Therefore, in 22 days they will complete 11/12 of the work. The remaining work = 1 - 11/12 = 1/12. On the 23rd day, A works and completes 1/20 of the work. Since 1/20 < 1/12, A completes part of the remaining work. Work remaining after A's work = 1/12 - 1/20 = (5-3)/60 = 2/60 = 1/30. On the 24th day, B works and completes 1/30 of the work. Therefore, the work is completed in 24 days.

3Hard

A can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. If A, B and C start working at it alternatively, starting from A, then B and then C, then how long will they take to complete the work?

  1. A.4 daysCorrect
  2. B.5 days
  3. C.4 1/2 days
  4. D.5 1/2 days

Solution

A's one day work = 1/10. B's one day work = 1/12. C's one day work = 1/15. Work done in 3 days = 1/10 + 1/12 + 1/15 = (6+5+4)/60 = 15/60 = 1/4. Therefore, the work will be completed in 4 * 3 = 12 days. The work will be completed in cycles of 3 days. The question is flawed as it has no correct answer. After 12 days, the work is complete. The closest value after dividing by 3 is 4. The actual answer should be 12 days.

Time & Work — Frequently Asked Questions

What is the LCM method in time & work?

Assume the total work equals the LCM of the given days, so each person's one-day work becomes a whole number. It replaces fraction arithmetic and is the standard approach for exam-pattern questions.

How are pipes-and-cisterns questions different?

They are time & work with a negative worker: an emptying pipe subtracts its rate. Everything else — LCM totals, combined rates — works identically.

How many Time & Work practice questions does Parikshala have for IBPS PO?

18 exam-pattern Time & Work questions for IBPS PO Quantitative Aptitude, each with a step-by-step solution. Practice is free — no sign-up needed to start.

More IBPS PO Quantitative Aptitude Topics

Every topic links to its own practice set with solutions.

Join Our Telegram Community

Daily GK questions, exam notifications, free mock test links, and peer discussion

Join Channel

Practice Time & Work for IBPS PO

18 exam-pattern questions with step-by-step solutions. Start free — no sign-up needed.