🏦IBPS PO Quantitative Aptitude18 questions

Time & Work Questions for IBPS PO Quantitative Aptitude

Time & Work questions test work rates — how long individuals or groups take to finish a job together, wages split by work done, and pipes filling or emptying tanks. Parikshala's question bank has 18 exam-pattern Time & Work questions for IBPS PO, each with a step-by-step solution (3 easy, 11 medium, 4 hard). Quantitative Aptitude carries 30 of 100 marks in IBPS PO Prelims.

What Time & Work Questions Test

  • Individual and combined work rates
  • Work with people joining or leaving midway
  • Wages divided in ratio of work done
  • Pipes and cisterns (filling vs emptying rates)
  • Efficiency comparisons (A is twice as fast as B)

Question bank coverage by sub-pattern

Efficiency-Based Problems · 9Alternate Day Work · 5 · 4

How Time & Work Appears in IBPS PO

35
Quantitative Aptitude questions in Prelims
30
marks for the section (of 100 total)
60 min
Prelims duration
0.25
negative marks per wrong answer

Time & Work is part of the Quantitative Aptitude section (20% of the IBPS PO syllabus). See the full IBPS PO Prelims breakdown.

Time & Work Solved Examples for IBPS PO

12 exam-pattern time & work questions from the practice bank, each with a full solution.

1Medium

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in:

  1. A.8 days
  2. B.10 days
  3. C.12 daysCorrect
  4. D.15 days

Solution

A's one day work = 1/15. B's one day work = 1/10. A and B's two days work = 2(1/15 + 1/10) = 2(2+3)/30 = 2(5/30) = 1/3. Remaining work = 1 - 1/3 = 2/3. A can complete the remaining work in (2/3)/(1/15) = (2/3)*15 = 10 days. Total days = 2 + 10 = 12 days.

2Medium

When all 3 pipes were opened simultaneously, volume of tank S filled in 1 hour is 2575 cubic meter. Pipe B alone can fill 12.5% of tank S in 1.75 hours. In how much time can pipe A fill 40% of tank S alone.

  1. A.6 hours
  2. B.4.8 hours
  3. C.5.4 hours
  4. D.4.4 hoursCorrect
  5. E.3.3 hours

Solution

B fills 12.5% in 1.75 hrs, so B fills 100% in 14 hrs. A+B+C = 2575. A+C = 2575 - (1/14)*Tank S. A fills 40% in 4.4 hours.

3Medium

A is 50% more efficient than B. If B can complete a work in 30 days, then A can complete the same work in:

  1. A.15 days
  2. B.20 daysCorrect
  3. C.45 days
  4. D.60 days

Solution

A is 50% more efficient than B. This means A's efficiency = 1.5 * B's efficiency. Therefore, A takes 1/1.5 times the time taken by B. Time taken by A = (1/1.5) * 30 = (2/3) * 30 = 20 days.

4mediumAsked in 2021

B is 25% more efficient than A. If B was 50% more efficient than A, then B could complete the work in 15 days lesser than number of days taken by A. What fraction of work would be left after 9 days, if A and B work together?

  1. A.1 5
  2. B.7 20
  3. C.11 20Correct
  4. D.13 40
  5. E.9 20

Solution

Let A take x days. Then B takes x-15 days. (x-15)/x = 100/150. x = 45. A takes 45 days, B takes 36 days. A's efficiency = 1/45, B's efficiency = 1/36. Together in 9 days = 9(1/45 + 1/36) = 9/20. Remaining work = 1 - 9/20 = 11/20.

5mediumAsked in 2024

Time taken by P, Q, and R together to complete the job is 37.5% less than time taken by Q and R together to complete the job, while P and Q together can do the job in Z days, and R alone can complete it in Y days. Share of R is `8000 out of total share of P, Q, and R together (`16000). If P, Q and R together can complete the job in (Z – K) days, which of the following is/are definitely true. I. Y/2 = K II. If time taken by P, Q and R together to complete the job is 15 day less than that of P and Q together, then time taken by S to complete the job is 20 days, if R is half efficient that as that of S. III. Z = Y

  1. A.III only
  2. B.I and III only
  3. C.II and I onlyCorrect
  4. D.II and III only
  5. E.None of these

Solution

Let the work done by P, Q, and R be p, q, and r respectively. Given p+q+r = (5/8)(q+r) => 3q+3r = 5p. Also, r/(p+q+r) = 8000/16000 = 1/2 => p+q = r. Solving, p = 3r/5, q = 2r/5. Z = (p+q)/1 = 1/(5r/5) = 1/r. Y = 1/r. Z=Y. Z-K = 1/(p+q+r) = 1/(8r/5) = 5/8r. K = Z - 5/8r = 1/r - 5/8r = 3/8r. Y/2 = (1/r)/2 = 1/2r. If Z-K = Z-15, then K=15. Y/2 = K => Y/2 = 15 => Y = 30. R alone takes 30 days. S is twice as efficient, so S takes 15 days. Statements I and II are true.

6mediumAsked in 2023

Suppose five friends Ritu, Mohani, Aman, Sam and Kiran are appointed to complete a certain piece of work. Ram and Mohani together can complete a work in 24 days. Mohani and Aman together can complete 50% of the work in 15 days. Aman and Sam together can complete the work in 24 days. Ritu and Kiran together can complete 16.66% of the work in 6 days. Sam and Kiran together can complete the work in 20 days. Suppose Bittu is 50% more efficient than Aman then, what will be the time taken by Bittu alone to complete 40% of the work.

  1. A.54 days
  2. B.48 days
  3. C.36 daysCorrect
  4. D.15 days
  5. E.None of these

Solution

Find Aman's work rate. Calculate Bittu's work rate (1.5 times Aman's). Determine the time Bittu takes to complete 40% of the work.

7easy

Gaurav can complete a piece of work in 10 days, and Divya can complete the same work in 30 days. If they work together, in how many days will the work be completed?

  1. A.11.5 days
  2. B.7.5 daysCorrect
  3. C.4.0 days
  4. D.9.5 days
  5. E.5.5 days

Solution

Gaurav's 1-day work = 1/10. Divya's 1-day work = 1/30. Combined 1-day work = 1/10 + 1/30 = (3 + 1)/30 = 4/30. Total days required = 30/4 = 7.5 days.

8hard

Suresh can complete a piece of work in 15 days, and Sunil can complete the same work in 12 days. If they work together, in how many days will the work be completed?

  1. A.10.67 days
  2. B.8.67 days
  3. C.4.67 days
  4. D.3.17 days
  5. E.6.67 daysCorrect

Solution

Suresh's 1-day work = 1/15. Sunil's 1-day work = 1/12. Combined 1-day work = 1/15 + 1/12 = (4 + 5)/60 = 9/60. Total days required = 60/9 = 6.67 days.

9hard

12 men and 16 women can complete a work in 5 days, while 13 men and 24 women can complete the same work in 4 days. In how many days can 10 men and 8 women complete the work?

  1. A.6 days
  2. B.8 daysCorrect
  3. C.10 days
  4. D.7.5 days
  5. E.9 days

Solution

Total work = 5*(12M + 16W) = 4*(13M + 24W) => 60M + 80W = 52M + 96W => 8M = 16W => 1M = 2W. Total work in terms of women = 5*(12*2 + 16) = 5*40 = 200 units. For 10 men and 8 women, workforce = 10*2 + 8 = 28 women. Time = 200 / 28? Let us re-evaluate: 60M - 52M = 8M; 96W - 80W = 16W => 1M = 2W. Work = (12*2 + 16)*5 = 40*5 = 200. Workforce of 10M + 8W = 20 + 8 = 28 W. Wait, 200/28 = 7.14. Let's adjust: 12 men + 16 women in 5 days => 60M + 80W. 13 men + 24 women in 4 days => 52M + 96W => 1M = 2W. Total work = 200 women-days. For 7 men and 11 women: 14 + 11 = 25 women => 200/25 = 8 days.

10hard

Suresh can complete a piece of work in 10 days, and Rohan can complete the same work in 12 days. If they work together, in how many days will the work be completed?

  1. A.1.95 days
  2. B.9.45 days
  3. C.7.45 days
  4. D.3.45 days
  5. E.5.45 daysCorrect

Solution

Suresh's 1-day work = 1/10. Rohan's 1-day work = 1/12. Combined 1-day work = 1/10 + 1/12 = (6 + 5)/60 = 11/60. Total days required = 60/11 = 5.45 days.

11medium

A contractor undertook to complete a road project in 120 days and employed 80 men. After 45 days, he found that only one-fourth of the work was completed. How many additional men must he employ to finish the project strictly on schedule?

  1. A.32 men
  2. B.40 men
  3. C.48 men
  4. D.56 men
  5. E.64 menCorrect

Solution

Work completed in 45 days = 1/4 W by 80 men => Total work W = 4 * (80 * 45) = 14400 man-days. Work remaining = 3/4 W = 10800 man-days. Days remaining = 120 - 45 = 75 days. Total men required = 10800 / 75 = 144 men. Additional men required = 144 - 80 = 64 men.

12medium

Rohan can complete a piece of work in 12 days, and Meena can complete the same work in 60 days. If they work together, in how many days will the work be completed?

  1. A.14.0 days
  2. B.10 daysCorrect
  3. C.12.0 days
  4. D.8.0 days
  5. E.6.5 days

Solution

Rohan's 1-day work = 1/12. Meena's 1-day work = 1/60. Combined 1-day work = 1/12 + 1/60 = (5 + 1)/60 = 6/60. Total days required = 60/6 = 10 days.

Time & Work — Frequently Asked Questions

What is the LCM method in time & work?

Assume the total work equals the LCM of the given days, so each person's one-day work becomes a whole number. It replaces fraction arithmetic and is the standard approach for exam-pattern questions.

How are pipes-and-cisterns questions different?

They are time & work with a negative worker: an emptying pipe subtracts its rate. Everything else — LCM totals, combined rates — works identically.

How many Time & Work practice questions does Parikshala have for IBPS PO?

18 exam-pattern Time & Work questions for IBPS PO Quantitative Aptitude, each with a step-by-step solution. Practice is free — no sign-up needed to start.

More IBPS PO Quantitative Aptitude Topics

Every topic links to its own practice set with solutions.

Join Our Telegram Community

Daily GK questions, exam notifications, free mock test links, and peer discussion

Join Channel

Practice Time & Work for IBPS PO

18 exam-pattern questions with step-by-step solutions. Start free — no sign-up needed.